Demolition approval in Sydney: DA or CDC?

Which approval a Sydney house demolition needs: CDC or DA, neighbour notices, CDC conditions and disconnections, each linked to the official NSW source.

5.0 from 22 Google reviews
Wide street view of the screened site boundary
HaberfieldHouse demolition · Our work
View the work
  • Checked against the sources10 October2026
  • Sources11 linkedListed at the end of the guideSee the sources
  • Reading time3 min6 sections
  • Written by a licensed contractorAD204777NSW demolition licenceCheck the register

The short answer

Most Sydney house demolitions need either a complying development certificate (CDC) from council or a registered certifier, or a development application (DA) to council.

A CDC can be quicker, but in a heritage conservation area it only covers limited demolition, so taking down a whole house there goes through a DA.

In this guide8 sections

Exempt, complying or a development application

NSW has three routes. Exempt development needs no approval, but for demolition it only covers a minor structure, such as a shed or deck, that could itself be built as exempt development. A house is not in that group.

A complying development certificate (CDC) under the Demolition Code can cover a house, attached and detached structures including garages and pools, and industrial buildings. Council or a registered certifier issues it, and the Planning Portal says a CDC can be approved in as little as 20 days. Everything else goes to council as a development application (DA); the NSW Planning Portal is where both are applied for online.

Whichever route you take, the demolition itself has to follow the Australian Standard for demolition, AS 2601.

Check the property before choosing a route

A planning certificate (section 10.7) from the Planning Portal or your council shows the controls on your land. Check it for a heritage listing or a heritage conservation area first, because that decides the route.

In a heritage conservation area, a CDC only allows limited demolition, such as outbuildings and internal walls, so taking down the whole house there goes through a DA. A heritage item can’t be demolished as exempt development; ask your council early.

03Your situation

Which route fits your property

IfA house that isn’t heritage-listed or in a conservation area
ThenA CDC under the Demolition Code may be available; a certifier or council confirms.
IfA house in a heritage conservation area
ThenA DA, usually with a heritage impact statement.
IfA heritage item
ThenTalk to council first; it is not exempt development.
IfA shed or deck only
ThenPossibly exempt, if it could itself be built as exempt development.
IfPart of a new build
ThenCheck the build approval covers the demolition, with its own conditions.

The conditions that come with a CDC

A demolition CDC comes with standard conditions that shape the job. These are the ones customers ask us about most.

  • A waste management plan goes to the principal certifier at least 2 days before work starts.
  • Demolition runs 7am to 5pm, Monday to Saturday, with no work on Sundays or public holidays.
  • Where a neighbour’s wall is within 900 mm of the boundary, a dilapidation report on that wall is needed.
  • All essential services are disconnected under each authority’s requirements before work starts.
  • If more than 10 m² of bonded asbestos, or any friable asbestos, comes out, the certifier needs a signed contract with a licensed removalist and the landfill receipt. An owner-builder can’t remove it themselves.

Telling the neighbours

In metropolitan Sydney, the certifier or council tells neighbours within 20 metres about a CDC 14 days before it is approved. Then, before work starts, the applicant gives neighbours within 20 metres of the boundary 7 days’ written notice.

A DA is notified by council under its own community participation plan, so the rules differ from council to council. Our council guides cover what each council asks for, from heritage and trees to waste plans and road permits.

Services, SafeWork and the start date

Electricity, water and gas are disconnected before demolition by the people licensed to do it. For water, a licensed plumber disconnects the service at the main through Sydney Water’s Tap in. Ausgrid needs written approval from the owner, the occupier and the electricity retailer for a permanent disconnection.

Demolition of a load-bearing structure 6 metres or more high is licensed work, and the contractor notifies SafeWork NSW 5 calendar days before it starts. Licensed asbestos removal has the same 5-day notice. Build those days, and any approval conditions, into the start date.

Agree who does what, then send us the approval

Talk to your builder or designer about the site the next stage needs, and list the house, garage, sheds, pool, driveway and trees as staying or going. Then agree who lodges the application, who arranges reports and disconnections, and by when. Keep that list with the quote so nothing falls between you, your builder and us.

Send the address, plans and any approval you already have, with its conditions. If the approval is still in progress, say so, and we’ll plan the scope and preparation around it.

Official sources

Checked 10 October 2026. Your council or certifier confirms what applies to your property.

Get a free quote

Let’s make room
for what’s next.

Tell us what you’re planning and where the job is. We’ll talk through the work and arrange any site assessment needed for a written quote.

0402 548 0047 days a week · 7am–7pm
  1. We talk it throughYour plans, what stays and when your builder needs the block.
  2. We look at the siteWhere the job needs it, before we price the work.
  3. You get a written quoteThe scope, separately priced items and the agreed finish.
5.0 from 22 Google reviews

Tell us about the job

* Required fields

Your details
The site and the work
Work needed, what stays, access and timing.
Add photos or plans Optional
Up to 5 photos or PDF plans, 4 MB in total. You can add them in more than one go.
PDF plan requirements

Up to 100 pages, without passwords, comments, markups, fillable fields or scripts. If a PDF won’t go through, send photos of the pages instead.

We only use these details to reply to your enquiry. Privacy policy.