The demolition process, start to finish

How a Sydney house demolition runs, step by step: scope, approvals and notices, asbestos, safety, the demolition and handover. From over 30 years of jobs.

5.0 from 22 Google reviews
Excavator beside the remaining roof framing
HaberfieldHouse demolition · Our work
View the work
  • Checked against the sources10 October2026
  • Sources9 linkedListed at the end of the guideSee the sources
  • Reading time4 min8 sections
  • Written by a licensed contractorAD204777NSW demolition licenceCheck the register

The short answer

Every demolition runs in the same order: scope, then approvals, notices and disconnections, then any asbestos, then the building, then the clean-up and handover.

What changes from site to site is what has to stay, how people are kept clear and how the material gets out.

In this guide10 sections

Look at the site and agree the scope

Every job starts with what is coming down and what the site is like. We look at the building, access, anything that stays and the finish you need, using your plans and any asbestos report. Mention shared driveways, occupied buildings next door and changes in level.

The quote then says what is known, what still needs checking and what is excluded. This is the moment to settle the slab, garage, pool and anything else, so nobody has to guess on the day.

Approvals, notices and disconnections

The approval comes first: a CDC or a DA, with its conditions. Under a CDC, neighbours within 20 metres get 7 days’ written notice before work starts. Electricity, water and gas are disconnected by the people licensed to do it, and for licensed work the contractor notifies SafeWork NSW 5 calendar days ahead.

Set the start date once those pieces are in place, not before.

Keep people clear of the work

The work area is fenced off from everyone not on the job, with an exclusion zone wherever material could fall. On a street frontage that means temporary fencing, often screened, and signs for people walking past.

Agree how deliveries, visitors and trucks reach the site. Talk to the site contact rather than walking into the work area, and tell us before the scope is final if part of the property stays occupied.

Asbestos and salvage first

The materials in the house set the order of work. If there is asbestos, its removal, disposal and clearance happen before the main demolition.

If you want items salvaged, list them early. Whether something can be saved depends on the item, its condition and how it comes out.

The house comes down

The method suits the building and the site, and follows the Australian Standard for demolition, AS 2601. Neighbouring buildings must not be left weaker by the work, so walls near a boundary and anything that stays are planned for before the machine starts. We hose the rubble down to keep the dust down.

Under a CDC, demolition runs 7am to 5pm, Monday to Saturday. Questions and changes go through the site contact, and if something unexpected turns up, it is checked and agreed with you before any extra work starts.

Clear the block and hand it over

Material is sorted by type and trucked away as agreed. Removing the house, removing concrete and excavation are separate tasks, even on the same job.

At handover, walk the site against the agreed scope and collect the records: tip dockets, and any asbestos clearance certificate. Confirm what is left for your builder; the final check is about the next stage, not just whether the house is gone.

07Checklist

Check the handover between stages

  1. Assessment and scopeIs it written down what comes down, how we get in and what materials are known?
  2. PreparationWho confirms the approval, neighbour notice, disconnections and SafeWork notice?
  3. RemovalHow are the parts that stay protected, and how is asbestos handled?
  4. Clearance and handoverWhat is left on the block, and is it what your builder needs?

How long does a house demolition take?

As a standard guide, the machine work on a single-storey house typically takes 2–5 days on site once approvals and disconnections are in place; a double-storey house, or a sloping or tight site, takes longer. Counting the disconnections and any asbestos removal, the demolition stage typically runs 2–4 weeks. Those are typical published timings, not a promise: every job is different.

Much of the time goes on what has to happen before the machine arrives. One customer, Ben K., wrote in a Google review in August 2020: “The house was down in just over a week.” Tell us when your builder needs the block, and we’ll set out your timing with the quote.

  • Approvals: a CDC or a DA, and its conditions. The NSW Planning Portal says a CDC can be approved in as little as 20 days; a DA runs on council’s timeline, which averaged 84 days across NSW at 31 May 2026.
  • Notices and disconnections: under a CDC, neighbours get 7 days’ written notice before work starts, and licensed demolition needs 5 calendar days’ notice to SafeWork NSW. Electricity, water and gas are disconnected first: Energy NSW says removing the gas supply can take up to 20 business days, and electricity distributors typically need 10–15 business days’ notice.
  • Asbestos: removal, clearance and disposal come before the main demolition, with their own 5-day SafeWork notice for licensed removal.
  • Size and construction: the floor area, storeys and materials set how much there is to pull down, sort and truck away.
  • Access: the machines that fit and how trucks are loaded. A sloping block or tight entry takes a different approach from an open, level site, and under a CDC the work runs 7am to 5pm, Monday to Saturday.

Questions worth asking before the start

These questions help you understand the arrangements on your site.

  • Site contact: who can the owner and neighbours contact, and how are concerns handled?
  • Preparation: who confirms disconnections, assessments and notices before work starts?
  • Retained property: how are boundary walls, anything that stays and occupied areas protected?
  • Access: what arrangements apply to deliveries, visitors and shared driveways?
  • Unexpected findings: who assesses the issue and agrees any change to the scope?
  • Handover: what site condition and records are needed before the next trade?

Official sources

Checked 10 October 2026. Your council or certifier confirms what applies to your property.

Get a free quote

Let’s make room
for what’s next.

Tell us what you’re planning and where the job is. We’ll talk through the work and arrange any site assessment needed for a written quote.

0402 548 0047 days a week · 7am–7pm
  1. We talk it throughYour plans, what stays and when your builder needs the block.
  2. We look at the siteWhere the job needs it, before we price the work.
  3. You get a written quoteThe scope, separately priced items and the agreed finish.
5.0 from 22 Google reviews

Tell us about the job

* Required fields

Your details
The site and the work
Work needed, what stays, access and timing.
Add photos or plans Optional
Up to 5 photos or PDF plans, 4 MB in total. You can add them in more than one go.
PDF plan requirements

Up to 100 pages, without passwords, comments, markups, fillable fields or scripts. If a PDF won’t go through, send photos of the pages instead.

We only use these details to reply to your enquiry. Privacy policy.