House demolition cost in Sydney

What it costs to demolish a house in Sydney: our four price bands from $15,000 including GST, worked examples, and what is priced separately.

5.0 from 22 Google reviews
Overhead view of the demolition footprint and material piles
KillaraHouse demolition · Our work
View the work
  • Single-storey · 80–under 150 m²$15,000–$25,000Including GST
  • Single-storey · 150–under 250 m²$20,000–$35,000Including GST
  • Single-storey · 250–350 m²$30,000–$45,000Including GST
  • Double-storey · 200–350 m²$35,000–$55,000Including GSTWork out your range

The short answer

Knocking down a detached Sydney house costs $15,000–$55,000 including GST on our price bands, depending on floor area and storeys; a single-storey house of 150 to under 250 m² with reasonable access is $20,000–$35,000. That covers the house and its ordinary demolition debris, while asbestos, slabs and footings, pools, trees, excavation, approvals, utility disconnections and difficult access are priced separately.

In this guide8 sections

Price guide

Indicative house demolition prices

Indicative prices including GST. For a detached-house structure with reasonable access.

Floor area is the total across all storeys.

Single-storey house demolition — indicative prices including GST
Floor areaPrice inc. GST
80–under 150 m²$15,000–$25,000
150–under 250 m²$20,000–$35,000
250–350 m²$30,000–$45,000
Double-storey house demolition — indicative prices including GST
Floor areaPrice inc. GST
200–350 m²$35,000–$55,000

Priced separately

  • Asbestos
  • Slabs, footings and excavation
  • Pools and trees
  • Approvals and disconnections
  • Difficult access

Your written quote confirms what is included.

Worked examples from our price bands

These examples assume a detached house with reasonable excavator and truck access. They cover the house and its ordinary demolition debris; the separately priced work listed above is additional. Construction, access and the agreed finish determine where the quote falls within a band.

  • A single-storey house of 120 m²: $15,000–$25,000 including GST.
  • A single-storey house of exactly 150 m²: $20,000–$35,000. The first band stops just under 150 m², so a house right on the line moves up a band.
  • A single-storey house of 300 m²: $30,000–$45,000.
  • A two-storey house with 140 m² downstairs and 120 m² upstairs: 260 m² in total, so $35,000–$55,000.
  • A two-storey house under 200 m² or over 350 m² in total, a single-storey house under 80 m² or over 350 m², an attached house, a partial demolition or a tight site: outside the bands, so we price it from a site look.

How much to knock down a house of 16, 20 or 30 squares?

Builders, project home brochures and older plans often give a house’s size in squares. One square is 100 square feet, or about 9.29 m², so multiply the squares by 9.29 to get the floor area our bands use. For a two-storey house, count both floors.

The examples below use the same house-structure scope and separately priced work as the bands above. All prices include GST.

  • 16 squares: about 149 m². As a single-storey house: $15,000–$25,000.
  • 20 squares: about 186 m². As a single-storey house: $20,000–$35,000. A two-storey house this size is below the 200 m² band, so needs a site-specific price.
  • 30 squares: about 279 m². On one level: $30,000–$45,000. Across two storeys: $35,000–$55,000.

Extras are separate lines, not hidden in the band

The bands cover the house. Asbestos, slabs and footings, pools, trees, excavation, approvals, utility disconnections and difficult access are priced separately, each as its own line in the quote.

So if the 120 m² house above has asbestos eaves and a slab your builder wants out, the quote shows the house at its band price, then the asbestos removal and the slab as their own lines. Two quotes for the same house can describe different jobs, so compare line by line.

In a knockdown rebuild, what does the demolition cover?

The demolition scope ends at the agreed cleared block, including any of the additional work above that you have asked us to quote.

Your builder usually takes over with the set-out, earthworks, new service connections and the build, unless their contract says otherwise.

Compare both contracts before booking. Agree who covers approvals, disconnections, asbestos, concrete removal and the ground level at handover, so nothing is missed or charged twice.

What changes the price

The size and construction of the house set how much material there is and what kind. Access decides which machines can get in and how trucks are loaded. A sloping block, or a wall that has to stay, takes a different approach from an open, level site.

Asbestos and uncertain ground get their own assessment. A good quote names an unknown as unknown and explains how it will be checked and priced, rather than hiding it in a small allowance that makes the first total look lower than it is.

  • Building size, storeys and construction materials
  • Entry width, turning space and overhead wires
  • Asbestos reports and any material still to be tested
  • Slabs, footings, garages, pools and driveways
  • Waste removal, excavation and the finish your builder needs

Ask for a line-by-line scope

Run every quote through the same checklist. Who handles approvals, utility disconnections, fencing, removal, disposal and handover? Does each price include GST?

Keep the house and the optional extras apart when you compare. If one quote leaves out the pool or the concrete, get that price before deciding which is better value.

ItemWhat to make clear
Main houseBuilding size, storeys and construction; what is being retained.
Concrete and structuresSlabs, footings, driveway, garage and pool listed separately.
Asbestos and unknownsAvailable assessments, scope allowances and how additional work is priced.
Removal and handoverTransport, disposal and the site condition your builder expects.
Price basisGST, exclusions and the process for agreeing variations.

Get your own estimate in a minute

The demolition cost calculator uses the same four bands. Pick the house type and floor area, tell it about access and asbestos, and it shows your range with what it covers, then carries your answers into the quote form.

If your house sits outside the bands, or it is attached or partly staying, the calculator says so and a site look gives you a real price.

Send the details that matter

Send the address, the rough floor area, the number of storeys and photos from the street and around the house. Attach plans and any asbestos report you already have, and mark anything that has to stay.

Tell us what your builder needs at handover and when they want to start. We can coordinate approvals, utility disconnections, asbestos removal and clearance as part of your job, each shown as its own line in the quote.

Official sources

Checked 10 October 2026.

Get a free quote

Get your price
in writing.

Tell us what you’re planning and where the job is. We’ll talk through the work and arrange any site assessment needed for a written quote.

0402 548 0047 days a week · 7am–7pm
  1. We talk it throughYour plans, what stays and when your builder needs the block.
  2. We look at the siteWhere the job needs it, before we price the work.
  3. You get a written quoteThe scope, separately priced items and the agreed finish.
5.0 from 22 Google reviews

Tell us about the job

* Required fields

Your details
The site and the work
Work needed, what stays, access and timing.
Add photos or plans Optional
Up to 5 photos or PDF plans, 4 MB in total. You can add them in more than one go.
PDF plan requirements

Up to 100 pages, without passwords, comments, markups, fillable fields or scripts. If a PDF won’t go through, send photos of the pages instead.

We only use these details to reply to your enquiry. Privacy policy.