Skip to content

Clear today. Build tomorrow.Demolition and excavation across Sydney

Open 7 days · 7am–7pm

Council rules guide · Checked 10 October 2026

Demolition rules in Willoughby City Council

What Willoughby Council asks before a demolition: heritage and tree rules, its 85% recycling waste plan, damage deposits and road permits, from its own DCP.

5.0 from 22 Google reviews
Overhead view of the house demolition, excavator and truck
KillaraHouse demolition · Our work
View the work
  • Checked against the sources10 October2026
  • Sources11 linkedFrom the council’s own pagesSee the sources
  • Reading time3 min7 sections
  • Written by a licensed contractorAD204777NSW demolition licenceCheck the register

The short answer

In Willoughby, a house that isn’t heritage-listed or in one of council’s 12 heritage conservation areas can go through a CDC under the state Demolition Code if it meets the code; otherwise it needs a DA with a heritage impact statement, and council doesn’t support demolishing heritage items or contributory buildings.

Trees over 4 metres, an 85% recycling target and a damage deposit set by the project’s cost shape most jobs.

In this guide9 sections

CDC or DA in Willoughby

Willoughby’s development control plan (DCP 2023) doesn’t have its own demolition chapter. It points to the state Demolition Code for complying development, and says a development application (DA) is needed when a proposal doesn’t meet all of a code’s criteria.

Council’s own CDC checklist (updated August 2022) asks for a demolition plan and waste plan details, the area and type of any asbestos (bonded or friable), and a structural engineer’s certificate where a wall is less than 0.9 metres from the boundary. If the work comes within 3 metres of a tree, the council tree permit has to be in hand before the CDC.

Heritage items and the 12 conservation areas

Willoughby has 12 heritage conservation areas, and council says its consent is needed for most changes to buildings in them. Part H of the DCP (version 3, July 2025) says council doesn’t support demolishing heritage items or contributory buildings, and considers it only where a building is not capable of retention or restoration.

Council won’t grant consent to demolish in a conservation area without considering what replaces it, so the new design goes in with the demolition application. A DA for a heritage item, land near one or anything in a conservation area needs a heritage impact statement, and a demolition that is approved needs an archival record of the building and grounds. Part H also asks for a heritage structural engineer’s report with these applications.

On the NSW planning maps, conservation areas cover about a third of the land in Artarmon and Castlecrag (the Griffin area), about a quarter of Naremburn and a fifth of Chatswood, where around 90 listed heritage items sit inside the suburb boundary.

03Your situation

What Willoughby asks, by situation

IfNot heritage, no trees near the work
ThenA CDC with a demolition plan, waste plan details and the asbestos type and area.
IfA wall within 0.9 m of the boundary
ThenA structural engineer’s certificate with the CDC.
IfWork within 3 m of a tree
ThenThe council tree permit before the CDC.
IfIn a conservation area or a heritage item
ThenA DA with a heritage impact statement, the replacement design and an archival record.

Trees: the 4 metre rule

Part G of the DCP needs a council permit to remove a tree over 4 metres high, with a girth over 600 mm at 1.4 metres, or with a crown spread over 3 metres. The permit is displayed on site from 72 hours before the work and while it happens.

On a heritage item or in a conservation area, council can’t issue a tree permit: the tree goes into a DA instead. For a DA, trees affected by the development, which council says includes demolishing a building, are assessed with the application, a tree protection plan is needed where retained trees could be affected, and replacement planting is at 3 trees for every 1 removed.

The waste plan: 85% recycled

Council’s Construction and Demolition Waste Management Plan form sets a target of salvaging and recycling at least 85% of demolition material. It lists what is coming out, what is reused or recycled and where the rest goes.

We sort brick, concrete, timber and metal on site and fill in the material side of the form with you, then give you the tip dockets for your records.

Damage deposits, skips and the street

Willoughby’s 2026–27 fees set a damage deposit by the estimated cost of the development, for example $3,400 for $50,000 to $99,999 and $4,700 for $100,000 to $499,999, with a $279.50 inspection fee to release it. Figures as listed on 10 October 2026.

  • Skip bin on the road: a $162.50 application fee and $261.50 for up to 3 days, for containers up to 6 m³.
  • Hoarding or builder’s fence in the road reserve: a hoarding permit, which council says takes about 3 to 4 weeks. The administration fee is $1,605 for a Class A or B hoarding and $1,400 for a builder’s fence. Hoardings then cost $27 per m² per week, or $41.50 in the Chatswood CBD and St Leonards; a builder’s fence on council land in a residential area is $23 per metre per week.
  • Trucks, concrete pumps, mobile cranes and lifts on the road: an occupation of public road permit, with a minimum of 10 business days to process.

Willoughby’s asbestos policy

Willoughby’s asbestos policy, adopted in 2013, says removal of any quantity is to be done by a licensed removalist, which is stricter than the state’s 10 m² line. Council’s fact sheet also says asbestos goes to a licensed landfill.

Our team removes non-friable asbestos under our Class B licence, and friable asbestos goes to a licensed Class A subcontractor named in your quote. Our jobs include a laundry and toilet in Middle Cove.

  • Ceiling space opened up after removal, showing the timber framing and ducting
    Our work
    Middle Cove, laundry and toilet: after

Suburbs in Willoughby City Council

These rules apply across the council area. Each suburb page has the local planning picture and how we work there.

Official sources

Checked 10 October 2026. Your council or certifier confirms what applies to your property.

Get a free quote

Let’s make room
for what’s next.

Tell us what you’re planning and where the job is. We’ll talk through the work and arrange any site assessment needed for a written quote.

0402 548 0047 days a week · 7am–7pm
  1. We talk it throughYour plans, what stays and when your builder needs the block.
  2. We look at the siteWhere the job needs it, before we price the work.
  3. You get a written quoteThe scope, separately priced items and the agreed finish.
5.0 from 22 Google reviews

Tell us about the job

* Required fields

Your details
The site and the work
Work needed, what stays, access and timing.
Add photos or plans Optional
Up to 5 photos or PDF plans, 4 MB in total. You can add them in more than one go.
PDF plan requirements

Up to 100 pages, without passwords, comments, markups, fillable fields or scripts. If a PDF won’t go through, send photos of the pages instead.